> For the complete documentation index, see [llms.txt](https://docs.strata.hendersonengineers.com/llms.txt). Markdown versions of documentation pages are available by appending `.md` to page URLs; this page is available as [Markdown](https://docs.strata.hendersonengineers.com/reference/exports/electrical-equipment-schedule.md).

# Electrical equipment schedule

Generate, copy, or download an electrical equipment schedule.

The Electrical Equipment Schedule lists all distribution-tier equipment in the project — main service, distribution boards, and panelboards — in hierarchy order.

> 📸 **Screenshot — Electrical Equipment Schedule** The schedule modal titled "ELECTRICAL EQUIPMENT SCHEDULE" with equipment listed in hierarchy order and the **Download PNG** button in the header.

***

## Opening the schedule

With **Electrical** selected in the discipline switcher, open the hamburger menu (≡) → **File** → **Export** → **Schedules**. The **Electrical Equipment Schedule** modal opens.

***

## Schedule columns

| Column   | Description                                                                                  |
| -------- | -------------------------------------------------------------------------------------------- |
| Name     | Equipment name as entered in the design environment                                          |
| Type     | Equipment type (Switchboard, Switchgear, Distribution Board, Distribution Panel, Panelboard) |
| Voltage  | The equipment's configured voltage (e.g., 208Y/120V 3Ø 4W, 480Y/277V 3Ø 4W)                  |
| Size (A) | Estimated size in Amps                                                                       |

Equipment is listed in hierarchy order: sources → distributions → branches (panelboards). When nothing is configured, the modal shows an empty state.

***

## Exporting

* **Download PNG** — exports the schedule as an image (`electrical-schedule.png`) with a white background and no UI controls.
* **Copy to Clipboard** — copies the schedule as both rich (HTML) and plain text, so it can be pasted into a document or spreadsheet.

***

## Notes

* Size (Amps) is a planning-level estimate, not a panel-schedule output.
* Space or circuit counts per panel are not included at this stage.
* For structured tabular data, use **File → Export → Grid Data** (see [Electrical Data View](/workflows/electrical-planning/data-view.md)).
* For visual overlays of the hierarchy on the floor plan, see the [Branch Map](/reference/exports/branch-map.md) and [Distribution Map](/reference/exports/distribution-map.md) exports.

***

## Related

* [Electrical Overview](/workflows/electrical-planning/electrical-planning-overview.md)
* [Hierarchy and Equipment](/workflows/electrical-planning/hierarchy-and-equipment.md)
* [Branch Map](/reference/exports/branch-map.md)
* [Distribution Map](/reference/exports/distribution-map.md)
* [Mechanical Equipment Schedule](/reference/exports/mechanical-equipment-schedule.md)